North expansion — Bethlehem Square / US 22
Planning phase. An independent plan; nothing is funded or built yet. What this means
Why here
Retail destination with possible park-and-ride near US 22, reached by extending the Spine north if ridership and funding justify it.
Program ideas Ideas if pursued · to study
- Park-and-ride and transfer if demand
Which extras are worth it here, maybe later, or not worth it is rated further down this page.
What exists today Existing today
No transit facility at this location is described in the plan.
Measured station area
- Elevation
- 112 m (USGS 3DEP)
Future train access Longer trip (extension only)
From Bethlehem Square / US 22, about 20 minutes on Bethlehem Connect to the rail-ready stop at Farrington Square.
No passenger trains run in Bethlehem today, and no regional rail route or station has been chosen. Rail-ready stops are where this plan would keep space free. How this was measured.
Measured links
- North expansion to Bethlehem Square: North Bethlehem → Bethlehem Square / US 22 · 5.62 km · ~11.2 min · max 6.5%
- Bethlehem Township park extension, from the North expansion: Bethlehem Square / US 22 → Bethlehem Twp. park · 5.24 km · ~10.5 min · max 5.8%
Still unknown
- Linden St redesign coordination
- Bethlehem Township coordination
Amenities here: worth it or not Screening judgment
Northern extension (+5.62 km) built only if demand appears, to a retail area near US 22 with no measured walkshed yet, where park-and-ride, terminus and driver needs apply only if it is built and the existing shops argue against adding food or retail.
Worth it here
None
Maybe later here
- Secure bike lockers or bike hub, and bike-share docks: Lockers only if the extension is built as a terminus or park-and-ride; bike share needs a measured walkshed and an operator.
- Park-and-ride: Network edge near US 22, but only if the extension is built, sharing retail lots by agreement, after measuring the walkshed.
- Drop-off and paratransit loading zone: A terminus would justify an accessible loading zone, but only if built; use existing retail curb space by agreement.
- Terminal bus charger (overhead pantograph): If extended, BSQ becomes the northern terminus; re-run the energy model and pick one northern charger site, here or NBETH.
- Solar panels on the station canopy: A shared retail lot isn't project land, so only if an account can take the credits (to confirm). No large carport here.
- Battery energy storage: Only if the northern terminal charger is built here and demand charges (still to be pulled) make peak trimming pay.
- Equipment-lending lockers or package lockers: Package lockers could suit a terminus or park-and-ride if a vendor installs them free (to confirm); no venue for lending lockers.
- Driver restroom and break room: If extended, this becomes the northern terminus and relief is needed from day one; use an existing building by agreement.
Not worth it here
- Heated, enclosed waiting room: No station exists yet, and at 112.4 m it isn't exposed; a wind-screened shelter suits a 10-minute terminus.
- Public restrooms: No station and no measured walkshed yet; check what nearby retail already offers (to confirm) before ever building.
- Staffed customer service: Not the main hub, with no measured trips or intercity links.
- Food or coffee kiosk (partner-run): Already a retail destination, so a kiosk would compete with existing shops; the walkshed isn't measured either.
- Small shop space: New retail would duplicate the shops already next door.
- Community lounge or study nook: A park-and-ride or terminus stop with no host partner.
- Water bottle filler: No known water service, trail, events or long waits here.
- Event queuing and bus staging space: No venue of about 5,000 seats or major festival is identified nearby.
- Elevators (in pairs), only at level changes: Any future stop would be curbside or lot-side with no level change.
- Ground-source heat pumps (enclosed spaces only): No enclosed space is planned.
- Public art and heritage or geology display: No documented heritage or geology tied to this stop in the project files.
- Snow-melt at the platform edge: At 112.4 m it's a valley-level stop, far below the ~200 m test; rely on snow clearing.
- Regional and intercity bus bays: No regional or intercity carrier stop or commitment is recorded here.
- Rail-ready space reservation: Not on the rail-ready corridor list (PNR, WIND, POLK, FARR).
- Hospital and 24/7 shift-worker features: No 24/7 employer of 2,000+ within 400 m; St. Luke's Anderson Campus is about a 7.5 km walk and not served.
- Energy display with real solar and charging data: No solar or charger meters exist here.
- Public Wi-Fi and phone charging: No enclosed waiting room is planned.
Every stop also gets the essentials. Ratings are the author's screening judgment from measured data, not a design or a commitment.